C0024 Pakistan

FP085: Green BRT Karachi

C0024 Pakistan

  • Tipo Queixa
  • Date received 23 Aug 2026

On 26 August 2026, the IRM registered a complaint, received on 23 August 2026, related to the implementation of GCF Project FP085 in Pakistan. The complainant(s) are members of Union Council-1, TMC Model Colony, Karachi, acting in their capacity as representatives and affected community members. The complainants have not requested confidentiality.

The complaint relates to GCF Project FP085, “Green BRT Karachi.” The project aims to build a zero emissions rapid bus transit system in the city of Karachi. Project activities include (i) construction of a bus rapid transport corridor of approximately 30 kilometers; (ii) operationalizing a biomethane hybrid bus fleet; (iii) flood proofing and improving transport corridors and (iv) construction of a biogas plant.

The complainants have brought to the IRM several concerns related to the implementation of the project. The complainants have alleged the following:

  • Destruction of water supply, gas and electric infrastructure due toconstruction works;
  • Improper disposal of construction debris, resulting in blockages tosewerage systems; and
  • Increased risk of flooding to roads due to construction activity;

As of 15 September 2026, the IRM determined the complaint to be eligible. 

Estado do caso

Aberto

23 Aug 2026

Queixa
Elegibilidade
Passos iniciais e escolha do processo
Fechado

Queixoso

Union Council-1, TMC Model Colony

Natureza do prejuízo apresentado

Community Health Safety and Security

Políticas invocadas do GCF

Environmental and Social Safeguards

Documentação

Título Versões
Carta de Reclamação
Inglês
Determinação da Elegibilidade
Inglês

Detalhes do projecto

Número do projectoFP085
Título do projecto Green BRT Karachi
Tema
Mitigação
Região
Ásia-Pacífico
Entidade Acreditada Asian Development Bank
Áreas de resultados
Transporte
Categoria do risco Categoria A